Site
Infrastructure

The first phase of work on site we are carrying out at Peddimore involves creating the site’s infrastructure.

This includes building a new roundabout on the A38 that will be the main access to the development, as well as creating internal roads, footpaths and cycleways.

Earthwork excavations are currently taking place to prepare the development’s main building plots. Our aim is to transport as little excavated material from the site as possible as part of our commitment to reducing HGV movements on local roads.

The material that we move is helping to create the many ‘bunds’, or mounds’ that will help to screen the buildings along with a planting scheme that will be delivered in a comprehensive manner as early as possible in the scheme’s lifetime.

Work on the main part of the site will be carried out from 07:00 to 19:00 Monday to Friday and 08:00 to 13:00 on Saturdays. Some work on the new A38 roundabout may take place outside these times.